caption freeform

Water Plant Upgrade

The City has made significant improvements to increase the drinking water output from 21 million gallons per day (MGD) to 30 MGD using newer treatment technology in the same water plant footprint. The City has ensured a continuous supply of safe drinking water to the residents of Highland Park; as well as, the neighboring communities served by this Plant during this process.  

Major Work Completed

  • Membrane Filtration System Facility built into existing portion of the Water Treatment Plant
  • Updated or built chemical storage areas
  • Decommissioned the old Conventional Filter System
  • Installed new Low Lift Pumps
  • Installed new diesel generators
  • Installed new Access Control and CCTV systems
  • Updated boilers and ancillary systems
  • Installed new HVAC system
  • Repaved and stripped the surrounding asphalt
  • Roof and internal demolition and rebuild of the Wash Water Reclamation Building
  • Supervisory Control and Data Acquisition (SCADA) integration of new equipment
  • Installed new Security and Fire Alarm systems
  • Clearwell improvements
  • Installed new Automatic Transfer Switches, Switchgear and Transformers
  • Painted and insulated pipes
  • Updated the restroom and Water Treatment Plant to be ADA compliant

Before Construction

  • Construction bids opened on November 16, 2012 and was awarded to Joseph J. Henderson & Son, Inc.
  • The consideration of adoption of the Upgrade Project was presented to City Council during the December 10, 2012 City Council Meeting.
  • On January 14, 2013 the pilot program arrived at the Water Treatment Plant. The Illinois EPA requires two months of testing of the membrane filters. Pilots are small scale preliminary studies to evaluate the new filters prior to construction.
  • On February 8, 2013 a public kickoff meeting was held at the Police Station. Public Works Director, Ramesh Kanapareddy, introduced the team that will perform the Water Plant upgrade work. These include:
    • JJ Henderson & Son – General Contractor
    • Evoqua Water Technologies, Inc. (formerly known as Siemens Water Technology) - Membrane Filtration System CDM Smith - Design Engineers
    • Cummin NPower - Generators
    • Commonwealth Edison - Power Supply Upgrade
    • On hand to meet the team were Councilman Blumberg, then Deputy City Manager Ghida Neukirch, Village Managers and staff of the City’s wholesale water system partners: Deerfield, Lincolnshire and Bannockburn; as well as, representatives of the North Shore Sanitary District and the Park District of Highland Park.
  • The groundbreaking celebration held at the Water Plant on February 15, 2013 was attended by our Mayor and Council members Higginson, Blumberg, Frank and Kaufman. They were joined by former Mayors Pierce and Geraci, elected officials and staff from Deerfield, Highland Park Park District, School District 112, Highland Park Library Board, contractors, design engineers, residents and City staff to commemorate the culmination of 15 years of discussion and planning and the beginning of a two-year effort to upgrade the George B. Prindle Water Treatment Plant.
 
Low Lift Demo
Low Lift Torch
Basin 3
Clearwell drilling
West Raw Water 1
West Raw Water 2
Torch
New Mag Meter
Concrete Pour
Re-bar Walls