A subdivision is
the division or consolidation of a parcel or parcels of land into
one or more lots of record. The regulations set forth in the City
of Highland Park Subdivision Ordinance are designed to protect
Highland Park neighborhoods by establishing minimum lot depths,
providing for the proper location of streets, residences and alleys,
and ensuring new lots have proper water service and sanitary sewage
service.
This brochure is designed to provide an easy to understand, step-by-step
guide to the subdivision application process. This brochure is
not intended to be a substitute for City Ordinance Chapter 151;
Subdivision Regulations. The ordinance is available in its entirety
through
the Department of Community Development.
Processing
TimeThe City of Highland Park is committed to processing your
application in a professional and timely manner. You can prevent
unnecessary delays by submitting all necessary documents no later
than the designated deadline and by following the guidelines described
in the step-by-step process, which follows. Processing time will
vary on a case-by-case basis.
Major SubdivisionsOften, when large tracts of land are subdivided, new streets
must be created, water and other utility services are upgraded, and
other public improvements are required. These are considered MAJOR
subdivisions, and special review is necessary to ensure public improvements
are properly planned for and constructed. A major subdivision is any
subdivision that requires the installation of bonded improvements such
as stormwater detention facilities, sidewalks, streets, water mains,
and sewers.
As indicated in steps 1 through 12 of this booklet, a MAJOR subdivision
is processed in two states: preliminary plat and final plat. The
preliminary plat is reviewed first by the Plan Commission, and then
forwarded to the City Council with recommendation for either approval
or denial. Once the preliminary plat is approved by the City Council,
you will proceed to the final plat stage which will again be reviewed
first by
the Plan Commission, and then by the City Council.
Minor
SubdivisionsWhen two lots are consolidated into one lot, or a large lot
is split into two lots, there may be no change to existing public
improvements and no required bonded improvements. Any subdivision
that does not include the installation of bonded improvements and
requires no variations from the Subdivision of Zoning regulations
is a MINOR subdivision and is eligible for expedited processing.
Because MINOR subdivisions are less complex, they are processed
in a single stage with Plan Commission review followed by the City
Council action.
Step 1: Preliminary Staff MeetingTo begin the subdivision process, make an appointment to review
your proposal with one of the professional planners on the City staff.
The planner will describe the application process and discuss minimum
standards for lot depth, street depth, etc. Special considerations
such as stormwater management, flood plain regulations, and the Steep
Slope Ordinance will be reviewed if applicable. The planner will advise
you of additional materials, such as a tree preservation plan, that
may
be required for your proposed subdivision.
Finally, City staff will determine whether your proposal is a MINOR
subdivision or MAJOR subdivision.
Step
2: Preparing for Site Plan ReviewAfter meeting with the Planning staff, you will need to prepare
the following preliminary plans for Site Plan Review.
- Proposed layout and design of subdivision.
- Vicinity map showing project
site with surrounding area.
- Photographs of site and abutting properties.
- Other
information as required.
Step 3: Site Plan Review
City staff responsible for development review meets weekly as the interdepartmental
Site Plan Review Team (SPRT) to review development proposals and acquaint potential
applicants (owners, developers, and design professionals) with applicable ordinances.
You may schedule an appearance before the SPRT by contacting the Community
Development
Department.
Planning staff will facilitate the preliminary review of your subdivision
plat with the Site Plan Review Team. The purpose of this informal
meeting is to develop a staff position regarding any proposed development
project, and to identify and resolve any problems early in the development
process. This review should uncover issues associated with the plan
and help you identify any agencies outside the City, which need to
be involved.
Once the SPRT is confident the project is ready for Plan Commission
review, you will be scheduled for a pre-application discussion with
the Plan Commission. More than one meeting with the Site Plan Review
Team may be necessary before you are prepared for the pre-application
discussion.
Step 4: Pre-application Discussion
The pre-application discussion provides an opportunity for
you to receive early feedback from the Plan Commission. Two weeks
prior
to the pre-application discussion, you must submit a complete site
plan and a written description of your project to the Planning staff
who will prepare a formal report to the Plan Commission. At the pre-application
discussion, you or your representatives will make a brief presentation
regarding the proposal. The Plan Commission will inform you of any
questions or concerns it may have and may ask for additional information
about your proposal. You will then need to consider the Plan Commission's
comments
as you prepare for the next step.
Step 5: Submitting
Your ApplicationTwenty-one days prior to the scheduled public meeting, the
following information must be submitted to the Department of Community
Development.
For
a MINOR subdivision you will need to submit the following:
- Completed
Application Form.
- Application Filing Fee.
- Plat Subdivision - 5
copies, drawn to a scale no less than 1"=50' (24"x36"), and 1 reduced copy (11"x17").
- Plat
of Survey - 5 copies (24"x36") and 1 reduced copy (11"x17").
- Tree Survey - 5 copies, drawn to scale no less than 1"=30' (24"x36"),
and 1 reduced copy (11"x17") of affected trees and with a diameter
of six inches or greater.
- Title
Policy & Affidavit of Title.
- Site Context Plan
Step
6: Public NotificationFifteen days prior to the Plan Commission meeting, the City
will post on your site a notice indicating a public meeting will
be held
to review your application for subdivision.
The neighbors of your property must be provided with written notification
about your proposal and the upcoming
public meeting.
For a MINOR subdivision, upon receipt of your application, the
Department of Community Development will mail a notice to each
owner of property
abutting your site.
For a MAJOR subdivision, upon receipt of your application, the Department
of Community Development will mail a notice to each owner of property
abutting your site.
For a MAJOR subdivision, you must mail a notice to each owner
of property within 250 feet of your site. (Public rights-of-way
are
not counted toward the 250 feet distance requirement.) Planning
staff will prepare a map for you indicating the properties whose
owners
you must notify. Take the
map to Deerfield Township Assessor's office at 616 Laurel Avenue or the West
Deerfield
Township Assessor's office at 858 Waukegan Road in Deerfield to generate a
list of names corresponding to the property addresses.
All notifications must include the nature of the application and
the date and location of the meeting. A sample letter will be provided
to you, and all letters must be reviewed and approved by Planning
staff before they are mailed.
Step 7: Public Meeting and Plan Commission
ReviewAt the public meeting, planning staff will give a brief explanation
of the nature of your proposal. You may then state your case, and
members of the Plan Commission may question you. The public will
also be given an opportunity to speak, and anyone in opposition may
present opposing evidence and likewise be questioned by the Plan
Commission and you or your representative. You may then respond to
any objections.
If the Plan Commission desires more time for additional discussion,
it will continue its discussion at one or more additional meetings.
Once review of a MINOR subdivision is completed, the Department of
Community Development will make a written recommendation to the City
Council to either approve or deny the
plat of subdivision.
If you are proposing a MAJOR subdivision, the Plan Commission will
make a written recommendation to the City Council either to approve
or to deny your preliminary plat of subdivision. If it appears likely
that a variation of the Zoning Ordinance or Building Code will be
sought, the Plan Commission will reject the plat of subdivision or
exclude the non-conforming lots.
Step
8: City Council ActionFor a MINOR subdivision, once the City Council approves your
plat of subdivision, you have completed the subdivision process and
your plat can be recorded. (See Step 12.)
For a MAJOR subdivision, the City Council approval of the preliminary
plat allows you to begin preparation of the final plat, as outlined
in Step 9.
NOTE:
Steps 9 through 11 apply only to MAJOR SUBDIVISIONS.
Step
9: Submitting Your Final PlatOnce the City Council has approved your preliminary plat,
you have 90 days to prepare and submit a final plat which will include
detailed plans and specifications for the design and installation
of all bonded improvements such as sidewalks, streets, sewers, water
mains, and stormwater detention facilities. The City Engineer must
approve your plans and specifications for all bonded improvements
prior to submission of a final plat to the Plan Commission.
The final plat must also incorporate any changes required by the
City Council.
Step 10: Plan Commission Review of the
Final PlatOnce you have made any changes required by the City Council
and have obtained the City Engineer's approval for all bonded improvements,
the Plan Commission will review your final plat and forward a written
recommendation
to the City Council.
Step 11: City Council Action on Final
PlatThe City Council will review the recommendation of the Plan
Commission and will either approve or deny your final plat of subdivision.
If the Council approves the final plat, the approval will be subject
to certain development conditions that may include, but are not limited
to, the following:
- Securing approval from public utility companies and providing
necessary easements
on the final plat.
- Submission of a Subdivider's Agreement and letter of credit
guaranteeing the completion of all required bonded improvements.
- Submission of a waiver and covenant of the right to object
to a special assessment for future
improvements.
- Signatures of property owners, City Engineer, Mayor, City Clerk,
and Plan Commission Chair and Secretary.
Step 12: Recording Your
Approved PlatOnce all development conditions have satisfied and all fees
and costs paid, your approved plat will be recorded by planning
staff with the office of the Recorder of Deeds of Lake County,
Illinois.
Planning staff will send you a copy of the recorded plat. Please
note that the final plat of subdivision must be recorded within
the nine-
(9) months of the City Council's
approval, and no building permits can be issued nor can construction begin
before the plat has been recorded.
Contact Information
For more information, please contact the Department of Community Development,
1150 Half Day Road, Highland Park, IL 60035 at (847) 432-0867.
|